DYNAMIX GROUPConstruction at Luma continues to progress steadily across all three towers. While Tower A and Tower B have reached advanced stages of interior and finishing works, Tower C is moving ahead smoothly.
Here is the construction update:
Wing A & B -
* Flooring completed up to the 16th floor
* Lobby flooring and staircase tiles completed up to the 16th floor
* Fire-fighting work completed up to the 16th floor
* External paint completed
* Terrace waterproofing completed
Tower C -
* Ground floor slab casting completed
* Ground floor slab reinforcement work in progress
* Basement 3 to Basement 2 column reinforcement and casting in progress